Project Timeline
Hoisting the solar panels into place

Hoisting the solar panels into place.

Our Project Timeline

Cochrane High Students alongside the solar panels.

pic_left_turbine_cu

The Wind Turbine is now in place near to the solar panels.



Phase II Timeline

Sustainable Development Project Timeline

Project Progress

Sept 2005

 

 

Sustainable Development Committee Phase II born – 25 keen students spanning all grades

Sept 2005 – June 2006

 

 

Raised $30,000 through open house, private donations, grant applications

Dec 2006 – Jan 2007

 

 Possible installation of 10 new panels