| Spring 2008 |
Worked with CHSD committee members, RVS Maintenance and Grounds Departments to draft a plan and the costs for phase 4 |
| Summer 2008 |
Fundraised locally over summer |
| Fall 2008 |
Received full funding for phase 4 project |
| Fall 2008 |
Dug up garden beds south side of tennis courts Posted no idling signs in main parking lot Installed dual flush toilets
|
| Early spring 2009 |
Recycling bins purchased and recycling education program implemented in school |
| Spring 2009 |
Planted perennial garden Waterless urinals installed AirTap heat exchanger installed |
|