Spring 2008 Worked with CHSD committee members, RVS Maintenance and Grounds Departments to draft a plan and the costs for phase 4
Summer 2008 Fundraised locally over summer
Fall 2008 Received full funding for phase 4 project
Fall 2008 Dug up garden beds south side of tennis courts
Posted no idling signs in main parking lot
Installed dual flush toilets
Early spring 2009 Recycling bins purchased and recycling education program implemented in school
Spring 2009 Planted perennial garden
Waterless urinals installed
AirTap heat exchanger installed